No Project Service Location Periode Year
1 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan January 20th - 26th, 2013 2013
2 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan March 10th - 17th, 2013 2013
3 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan March 10th - 17th, 2013 2013
4 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan February 23rd - 28th, 2014 2014
5 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan March 1st - April 3rd, 2014 2014
6 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan June 3rd - 8th, 2014 2014
7 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan January 19th - February 5th, 2015 2015
8 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan March 29th - April 4th, 2015 2015
9 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan May 24th - 31st, 2015 2015
10 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan June 10th - 21st, 2015 2015
11 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan July 11th - 14th, 2015 2015
12 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan January 13th – February 5th, 2016 2016
13 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan March 2nd - 14th, 2016 2016
14 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan November 14th - 21st, 2016 2016
15 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan December 26th - 28th, 2016 2016
16 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan January 14th - 23rd, 2017 2017
17 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan August 5th - October 11th, 2017 2017
18 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan January 20th - March 21st, 2018 2018
19 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan August 6th - October 28th, 2018 2018
20 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan October 26th - November 9th, 2018 2018
21 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan March 5th - July 21st, 2019 2019
22 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan August 20th - 25th, 2019 2019
23 Re-install Refractory of Boiler 100 MW Unit 4 Tarahan Power Station Plant Refractory Lining PLTU Tarahan January 12th - 20th, 2020 2020
24 Re-install Refractory of Boiler 100 MW Unit 3 Tarahan Power Station Plant Refractory Lining PLTU Tarahan February 3rd - 15th, 2020 2020
25 Re-Install Refractory of Boiler 112Mw unit 2 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih November 26th – 30th, 2016 2016
26 Re-Install Refractory of Boiler 112Mw unit 1 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih November 30th - December 2nd, 2016 2016
27 Re-Install Refractory of Boiler 112Mw unit 1 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih April 27th - May 10th, 2017 2017
28 Re-Install Refractory of Boiler 112Mw unit 2 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih May 27th- June 1st, 2017/td> 2017
29 Re-Install Refractory of Boiler 112Mw unit 2 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih November 2017 2017
30 Re-Install Refractory of Boiler 112Mw unit 2 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih March 2018 2018
31 Re-Install Refractory of Boiler 112Mw unit 2 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih April - June 2018 2018
32 Re-Install Refractory of Boiler 112Mw unit 2 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih December 16th, 2018 - January 18th, 2019 2018
33 Re-Install Refractory of Boiler 112Mw unit 1 Teluk Sirih Power Station Plant Refractory Lining PLTU Teluk Sirih July - August 2019 2019
34 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang March 1st – 5th, 2017 2017
35 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang May 14th - May 23rd, 2017 2017
36 Re-Install Refractory of Boiler 110Mw unit 2 Sebalang Power Station Plant Refractory Lining PLTU Sebalang July 16th - 29th, 2017 2017
37 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang September 25th - October 3rd, 2017 2017
38 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang November 22th - December 1st, 2017 2017
39 Re-Install Refractory of Boiler 110Mw unit 2 Sebalang Power Station Plant Refractory Lining PLTU Sebalang January 3rd -7th, 2018 2018
40 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang April 28th - May 9th, 2018 2018
41 Re-Install Refractory of Boiler 110Mw unit 2 Sebalang Power Station Plant Refractory Lining PLTU Sebalang March 2018 2018
42 Re-Install Refractory of Boiler 110Mw unit 2 Sebalang Power Station Plant Refractory Lining PLTU Sebalang June 23rd - July 2nd, 2018 2018
43 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang January 18th - January 25th, 2019 2019
44 Re-Install Refractory of Boiler 110Mw unit 2 Sebalang Power Station Plant Refractory Lining PLTU Sebalang February 2nd - 10th, 2019 2019
45 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang June 23rd - 30th, 2019 2019
46 Re-Install Refractory of Boiler 110Mw unit 2 Sebalang Power Station Plant Refractory Lining PLTU Sebalang September 2nd - November 1st, 2019 2019
47 Re-Install Refractory of Boiler 110Mw unit 1 Sebalang Power Station Plant Refractory Lining PLTU Sebalang March 17th - June 29th, 2020 2020
48 Re-Install Refractory of Boiler 2x60Mw unit 1 Pulang Pisau Power Station Plant Refractory Lining PLTU Pulang Pisau February 2nd - 10th, 2019 2019
49 Re-Install Refractory of Boiler 2x60Mw unit 2 Pulang Pisau Power Station Plant Refractory Lining PLTU Pulang Pisau March 18th - 25th, 2019 2019
50 Re-Install Refractory of Boiler 2x10Mw unit 1 Ketapang Power Station Plant Refractory Lining PLTU Ketapang October 7th - 16th, 2019 2019
51 Re-Install Refractory of Boiler 2x10Mw unit 2 Ketapang Power Station Plant Refractory Lining PLTU Ketapang November 8th - 23rd, 2019 2019
52 Re-Install Refractory of Boiler Stocker 2x7Mw unit 1 Sanggau Power Station Plant Refractory Lining PLTU Sanggau July 12th - 23rd, 2020 2020
53 Dismantling & Installation Refractory Brick in Vertical Kiln Double Shaft (Cimprogetti) 450 Tpd Brick Lining PT. RAPP Riau May 11th - July 14th, 2015 2015
54 Refractory installation of Brick Kiln Tonasa V Brick Lining PT. Semen Tonasa May 28th - July 26th, 2013 2013
55 Insulation & Scaffolding Install vertical lime Kiln [Filter Dust Collector] Jacketing & Scaffolding Install PT. Batumas Mekar Agung May 28th - July 26th, 2013 2013
56 Insulation & Scaffolding Install vertical lime Kiln [Filter Dust Collector] Jacketing PT. Batumas Mekar Agung October 8th - 13th, 2014 2014
57 Insulation Thermal Ducting Pipe Stack & Fabrication Ventilator Ducting Jacketing PT. Batumas Mekar Agung November, 2014 2014
58 Recondition Refractory in Vertical Lime Kiln - Double Shaft (Cimprogetti) 150 Tpd Bricklining PT. Batumas Mekar Agung July 4th - 5th, 2016 2016
59 Recondition Refractory in Vertical Lime Kiln - Double Shaft (Cimprogetti) 150 Tpd Brick lining PT. Batumas Mekar Agung July 3rd - 10th, 2017 2017
60 Installation of Refractory Boiler 2x135 MW Refractory Lining PT. Cikarang Listrindo July 03rd - 10th, 2017 2017
61 Installation Refractory Brick in Vertical Lime Kiln Single & Double Shaft (MAERZ) 200 Tpd at New Greenfield Calcination Project Brick Lining PT. Bhumiadya Indonesia April 9th, 2016 - Mei 20th, 2017 2017
62 Installation Brick at Hot Gas Generator - Padalarang Brick Lining PT. Bhumiadya Indonesia June 27th - July 1st, 2016 2016
63 Refractory Installation Boiler 135 Mw unit 2 PLTU Banjarsari Refractory Lining PLTU Banjarsari November 4th - December 31st, 2016 2016
64 Refractory Installation Boiler 135 Mw unit 1 PLTU Banjarsari Refractory Lining PLTU Banjarsari May 30th - June 26th, 2017 2017
65 Refractory Installation Boiler 135 Mw unit 2 PLTU Banjarsari Refractory Lining PLTU Banjarsari October 31st - November 23rd, 2018 2018
66 Refractory Installation Boiler 135 Mw unit 1 PLTU Banjarsari Refractory Lining PLTU Banjarsari February 28th - March 28th, 2019 2019
67 Refractory Installation Boiler 135 Mw unit 2 PLTU Banjarsari Refractory Lining PLTU Banjarsari July 1st - 25th, 2019 2019
68 Refractory Installation Boiler 2x16.5 Mw unit 2 Refractory Lining PLTU Bolok April 28th - May 19th, 2018 2018
69 Refractory Installation stack / chimney 2x50MW Bengkayang – Singkawang Kalbar PT Praba Conserium Refractory Lining PT Praba Conserium May 29th - August 5th, 2017 2017
70 Refractory Installation Boiler 3x35MW unit 3 – Jeranjang NTB PT PLN Refractory Lining PT Praba Conserium May 29th - August 5th, 2017 2017