Project Information

Installation and maintenance of Refractory Lining on Boiler 112MW unit 1 and Boiler 112MW unit 2 at PLTU Teluk Sirih, Teluk Buo, Teluk Kabung Tengah, Padang City, West Sumatra

PT PLN (Persero)

Teluk Kabung, Sumatera Barat

Refractory Lining

PLTU Teluk Sirih

Project Timeline

The Refractory Lining Re-Install Project is carried out periodically over a period of time, as below:

Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
2016

Boiler 112Mw unit 1
November 30th - December 2nd, 2016


Boiler 112Mw unit 2
November 26th - 30th, 2016







2017

Boiler 112Mw unit 1
April 27th - May 10th, 2017
June 3rd - 8th, 2014

Boiler 112Mw unit 2
May 27th - June 1st, 2017
November 1st, 2017






2018

Boiler 112Mw unit 2
March 2018
April - June 2018










2019

Boiler 112Mw unit 1
July - August 2019


Boiler 112Mw unit 2
December 16th, 2018 - January 18th, 2019