Project Information

Installation and maintenance of 110MW Refractory of Boiler unit 1 at PLTU Sebalang, Tarahan, Kec. Katibung, South Lampung Regency, Lampung

PT PLN (Persero)

Kec. Katibung, Lampung Selatan

Refractory Lining

PLTU Sebalang

Project Timeline

The Refractory Lining Re-Install Project is carried out periodically over a period of time, as below:

Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
2017

Boiler 110Mw unit 1
March 1st - 5th, 2017
May 14th - 23rd, 2017
September 25th - October 3rd, 2017
November 22nd - December 1st, 2017

Boiler 110Mw unit 2
July 16th - 29th, 2017







2018

Boiler 110Mw unit 1
April 28th - May 9th, 2018


Boiler 110Mw unit 2
January 3rd - 7th, 2018
Maret 2018
June 23rd - July 2nd, 2018







2019

Boiler 110Mw unit 1
January 18th - 25th, 2019
June 23rd - 30th, 2019


Boiler 110Mw unit 2
February 2nd - 10th, 2019
September 2nd - November 1st, 2019







2020

Boiler 110Mw unit 1
March 17th - June 29th, 2020